Project Snapshot
| Category | Details |
| Client | BC Hydro |
| Project Name | High Precision Monitoring |
| Location | Fort St. John |
| Date | 2023 – 2026 |
Project Overview
Introduction
Following completion of BC Hydro’s Site C Earth Filled Dam near Fort St. John, BC, Underhill was engaged to deliver a high-precision monitoring program to track structural behaviour during and after reservoir filling.
The project involved monitoring 73 monitoring points across the dam with millimetre-level accuracy, requiring a robust and carefully designed control network capable of maintaining precision over time and under changing conditions.
Project Challenges
Delivering consistent, high-accuracy monitoring on this project required overcoming a range of environmental and operational challenges:
- Extreme seasonal temperatures ranging from +30°C to -40°C
- Dust, heat shimmer, strong winds, and ice fog affecting visibility and instrumentation
- Frosted prisms and variable GNSS reliability due to solar activity
- Ongoing construction and evolving site conditions
- Seismic events, including two earthquakes during the monitoring period
Underhill’s Approach
Underhill designed a monitoring solution anchored by a rigorously tested and adaptable control network. A pre-analysis using least squares adjustment initially proposed three primary control points, but this was expanded in response to field conditions—resulting in a network of 13 densified control stations for improved reliability.
The approach integrated complementary technologies and verification methods:
- GNSS observations for primary positioning control
- Trimble SX10 scanning total station for conventional measurements
- Precise levelling between all of the primary control to act as a independent verification of GNSS measurements
- Monitoring frequency was strategically adjusted to align with project phases, increasing from monthly to weekly and up to twice-weekly observations during critical reservoir filling periods.
Noteable Outcomes
- Successful monitoring of 73 monitoring points with consistent millimetre-level precision
- A resilient and adaptable control network that performed reliably in extreme conditions
- High-confidence data supporting dam performance evaluation during and after reservoir filling
- Improved field efficiency and data processing through optimized monitoring workflows
- This project was the recipient of a 2026 David Thompson Award for Challenging Non-Cadastral Project
Technical Highlights
- Pre-analysis and Least Squares Adjustment used to optimize network design and performance
- Control network expanded from 3 planned stations to 13 densified stations
- Independent verification through precise levelling across all primary control points
- The GNSS, robotic total station and levelling measurements were all processed with MicroSurvey’s StarNet Least Squares Adjustment software.
- GNSS accuracy achieved within 5–10 mm, with conventional measurements within 3–5 mm of control
- To strengthen the network of monitoring stations prisms, we included 20 Leica 360 prisms to allow for conventional ties from multiple primary control stations.
- Field productivity and office processing efficiency was substantially increased by introducing Trimble Access’s Monitoring module
Project Impact
Underhill’s monitoring program provided critical, high-precision data to support the safe filling and ongoing performance assessment of a major hydroelectric dam.
By delivering reliable results under extreme environmental and operational conditions, the project demonstrates Underhill’s ability to design and implement resilient geomatics solutions for complex infrastructure, supporting long-term asset performance and risk management.